The project has been assigned to the Saudi based construction company, Mohammed Al Ojaimi Establishment. the construction of a 110kV Transmission line for interconnection of Jeddah Solar Photovoltaic substation with the network. The approx route distance of OHTL is 14 km. The project value of the contract is $8.7 million. The contractor needs to complete the project within 23 months.
the project covers the design and construction of two 110kV OHTL to connect the Jeddah Solar PV Substation.
Once the project will be completed, Jeddah Solar photovoltaic substation will be connected to the network through Modon Substation.
The project covers using 2-402 Sq.mm ACSR/AW CONDOR conductor per phase and two OPGW along with the distance of the new line. The project details of work also cover the installation of Four circuits. The approx underground cable route distance is 1.55km.
The Contractor shall perform on a Lump-sum turnkey basis, the design, engineering, materials procurement, quality management, factory inspection/testing, transport and delivery to site, installation, construction, site inspection, testing and commissioning, all involved work and services until final handing over of new OHTL work in a satisfactorily working and operating condition.