Bahrain’s Tatweer Petroleum W.L.L declare the bid results for the “Engineering, Procurement and Construction (EPC) of Pre-Unayzah Gas Well Hook-Ups, included Pipelines and Tie-ins at Gas Dehydration Units”
A total of three firms has submitted the offer. Petrofac International (Bahrain) SPC, a subsidiary of UK based Petrofac has submitted the lowest bid price USD $49,283,196.
Other companies, WorleyParsons Services PTY Ltd Foreign Branch USD $75,543,008.570 and TDE Overseas Ltd. USD $99,362,000.000 has submitted their offers.
Project details:
The project field of work includes connecting a total of 24 Pre-Unayzah (PU) wells consisting of vertical wells and horizontal wells to the existing gas dehydration unit (GDUs).
The maximum expected gas flow from the vertical and horizontal wells is 30 Million standard cubic feet per day and 50 Million standard cubic feet per day respectively.
The line up of PU Wellheads to GDUs will enable the operation of GDUs at their rated capacity of 66 million standard cubic feet per day.
The contractor required to complete the project activities on a lump-sum turnkey basis including engineering, procurement, and Construction (EPC).