Oman have awarded $654 million Adam Thumrait dualisation road project

Oman’s Ministry of Transport and Communications assigned project” Construction of three segments of the Adam-Thumrait dualization road – Part 3, 4 & 5”.

The total value of the signed contract is $654 million.

The total distance of the Adam to Thumrait Road project is around 717 km including Part 1 & 2 under construction.

The remaining distance for the proposed project is around 400Km and it is split into Parts 3, 4 & 5, which is to be built as a new two-lane road adjacent to the existing road. The new road together with the old road forms the 4-lane dual carriageway.

  • Adam – Thumrait Road, Part – 3 – 132.5km
  • Adam – Thumrait, Part – 4 -135km
  • Adam – Thumrait Road, Part – 5 -132.5km

Adam – Thumrait Road, Part – 3 :

The Ministry signed the contract of value USD 192194770.36.

During January 2020, the Ministry received the offer from a total of eight bidders. Oman based Construction Company, Ghantoot Transport, and General Trading LLC has presented the lowest bid. (read more)

Part 3 includes the carriageway from Haima to Muqshin, of total road distance 132.5km.

It includes the construction of sixteen At-grade U-turns, service roads, 4 rest spot, 2 weigh stations, 21 lay bays, 8 emergency median openings, 22 ROP parking, approximately 115 reinforced concrete box culverts for over drainage and 88 pipe culverts for median drainage, median dame, and embankment protection.

Part 3 also includes the rebuild of existing road at wadi locations and removing part of the present road, protection works, and culverts, and providing new multi-cell box culverts at existing floodways locations.

Adam – Thumrait, Part – 4:

Ministry signed the deal of value USD 298771689.21. The Project has been assigned to Galfar Engineering & Contracting SAOG.

During January 2020, The Ministry got the proposals from a total of six bidders. Oman based Construction Company, Galfar Engineering and Contracting (GEC) has submitted the lowest bid.

Part 4 includes the construction of a new carriageway from Miqshin to Duka, of total road distance 135km.

It comprises the construction of 16 At-grade U-turns, service roads, 3 rest areas, 25 lay bys, 8 emergency median openings, 25 ROP parking, approximately 241 reinforced concrete box culverts for over drainage and 95 pipe culverts for median drainage, median dam, and embankment protection. Part 4 also comprises the reconstruction of existing road at wadi locations and removing part of the present road, protection works, and culverts, and providing new multi-cell box culverts at existing floodways locations.

Adam – Thumrait Road, Part – 5:

Ministry signed the contract of value USD $162140854.46.

During January 2020, The Ministry received the proposals from a total of 8 bidders. Oman Gulf Company has submitted the lowest bid.

Part 5 includes the carriageway from Duka to Thumrait, of total road distance 132.5km.

It comprises construction of 20 At-grade U-turns, service roads, 5 rest spot, 1 weigh station, 16 lay bays, 8 emergency median openings, 25 ROP parking, approximately. 101 reinforced concrete box culverts for over drainage and 110 pipe culverts for median10 pipe culverts for median drainage, median dam and embankment protection. Part 5 also includes the rebuild of existing road at wadi locations and removing part of the existing road, protection works, and culverts, and providing new multi-cell box culverts at existing floodways location. The project completion duration for each of the parts is three years apart from a 90-day mobilization period.

Parsons International & Company LLC is the consultant for the Ministry of Transport in the proposal and inspection of the Adam-Thumrait road dualization project.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Most Popular

Hill International secured $318 million Egyptian hospital revamp project

Hill International has secured a contract to provide construction management services for the $318m Kasr Al-Ainy Hospitals refurbishment project for Cairo University...

Actis eyeing $4.5bn fund for Mena renewable energy projects

Actis, an emerging markets investment firm based in London, UK, is eyeing finance worth $4 billion for launching its new international fund...

Abu Dhabi waste energy projects

The Abu Dhabi National Energy Company (Taqa), Emirates Water and Electricity Company (Ewec), and the Abu Dhabi Waste Management Centre (Tadweer) have...

SWPC invites to submit EOI for the Ras Mohaisen IWP

Saudi Arabian Company SWPC has invited developers to submit expressions of interest (EOI) for the planned Ras Mohaisen independent water project (IWP).